Colocation security teams usually want five things before an external de-racking crew enters a data hall: a site-specific RAMS, a step-by-step method statement (often called a method of procedure), a permit to work, proof of insurance and competence, and named crew and escort details. Requirements differ by operator and emirate, so request the operator's contractor pack first.
Key takeaways
- RAMS is your risk assessment plus method statement. The permit to work is the facility's sign-off to start a specific job.
- Generic, templated documents are the quickest way to get turned away.
- The facility isolates power, not the removal crew.
- Submit early, and match crew names exactly to the ID you'll show at the gate.
What is the difference between RAMS, a method statement and a permit to work?
RAMS (risk assessment and method statement) is the document pair you prepare: hazards and controls, plus the work sequence. A permit to work is the facility's authorisation to start a specific task at a specific time and place, usually issued after RAMS approval and closed out afterwards. In data halls, a method of procedure often sits alongside.
The three do different jobs, and operators often ask for all of them.
| Document | What it covers | Who prepares it | Who approves it | Common reason it's rejected |
|---|---|---|---|---|
| RAMS | Hazards, who could be harmed, controls | Contractor | Facility security or EHS team | Generic text, no mention of that hall |
| Method statement or method of procedure | Step-by-step sequence, roles, isolation, rollback | Contractor, with the customer | Facility operations or change board | Steps don't match the rack list |
| Permit to work | Authorisation for a defined task, location and time window | Applied for by the contractor | Facility, as issuing authority | Applied for before RAMS approval, or the window expires |
| Access request | Named people, dates, escort | Customer or contractor | Security | Names don't match ID |
Sharjah's OSHJ Code of Practice on permit to work says each permit should have a clearly defined scope of work, and that work should follow an appropriate risk assessment (OSHJ CoP 34. The same logic runs through most operators' packs.
What do colocation security teams check before letting a de-racking crew in?
Expect checks on identity, a named crew list, insurance certificates, approved RAMS and method statement, a permit to work for the date and hall, a tool and equipment list, escort arrangements and a booked loading-bay slot. Missing any one item can delay access.
Operators outside the UAE show the same pattern. One UK facility requires contractors to supply method statements and risk assessments, and a US university standard requires removal requests through a ticketing system before any action is taken. UAE operators publish less, so ask for the contractor pack in writing.
What to have ready:
- Named crew list with ID details, matching what each person will present
- Insurance certificates at the level the operator specifies
- Competence evidence for lifting, working at height and any electrical tasks
- Tool and equipment list, checked in and out
- Escort details and who the facility contact is
- Loading-bay and goods-lift booking
- Gate passes, where the building or free zone needs them
What should a de-racking method statement contain?
A de-racking method statement lists the scope, rack and asset list, sequence of steps, isolation and power-down confirmation, lifting and manual handling plan, floor protection, cable and fixing removal, waste and data-media handling, emergency actions, and who is responsible for each step. It should be specific to that hall, not a template.
Who isolates the power?
The facility does, or its authorised electrician. The removal crew shouldn't switch off breakers or unplug live feeds that belong to the landlord. The method statement should say who isolates, how de-energisation is verified, and how the isolation is tagged and released. Our guide to cage handback covers power circuits and what the operator expects back.
Lifting, floor loading and raised-floor work
Racks, disk shelves and UPS units are heavy, so the plan should state the lifting aids, the route, lift capacity and floor protection. Raised floors need extra care. One UAE operator checklist says tiles can't be opened without data centre staff approval and attendance, and a US university's procedures say the same about work below the floor. Ask before anyone lifts a tile.
Data media and waste
State what happens to drives before they leave the hall: sealed, counted and logged, or destroyed on site. List waste streams, including batteries and packaging, and who takes them away. Where equipment is being decommissioned, colocation agreements commonly cover timelines for equipment removal and data destruction requirements, as law firm Morgan Lewis notes, so check your contract too.
Which risks should the RAMS cover in a data hall?
A data hall RAMS should cover manual handling and heavy equipment, electrical isolation, working at height, raised-floor loading, fire detection and gas suppression, trip and dust hazards, and the security rules of a shared space. Each risk needs a named control, an owner and a stop condition, not a generic line.
| Risk | Example control | Heavy equipment |
|---|---|---|
| Heavy equipment | Lifting aids, two-person lifts, route check | Weights, lift capacity, lifting plan |
| Electrical | Facility isolation, verified de-energisation, tagging | Isolation record |
| Working at height | Approved steps or platform, overhead tray rules | Competence evidence |
| Raised floor | Floor protection, approved tile lifting | Route plan, attendance |
| Fire and suppression | No hot work, detector awareness, evacuation plan | Briefing record |
| Dust and debris | Controlled cable pulling, cleanup | Housekeeping plan |
| Work stays inside the cage, no contact with other cages | Work stays inside the cage, no contact with other cages | Cage boundary check |
| Security | Photography ban, device rules, escort | Signed rules |
How do requirements differ across Dubai, Abu Dhabi and Sharjah?
Abu Dhabi entities work under the OSHAD-SF occupational safety framework, Sharjah has an OSHJ code of practice on permit to work, and Dubai sites follow Dubai Municipality requirements plus the operator's own rules. Free zones may add their own permit systems. Ask each facility for its contractor pack instead of assuming a template.
OSHAD-SF is Abu Dhabi's occupational safety and health framework, supervised by the Abu Dhabi Public Health Centre. In practice, many UAE operators run their own permit system on top of whichever framework applies. Treat the operator's pack as the rule for your visit.
What mistakes get de-racking crews turned away?
The usual mistakes are generic RAMS, names that don't match ID, late submission, no isolation plan, no tool list, and unapproved raised-floor work. Most are paperwork gaps you can close days earlier.
- A template RAMS that never mentions the hall, rack numbers or access route.
- Crew changes at the last minute, so names on the list no longer match.
- Crew trying to isolate power that belongs to the landlord.
- No lifting plan for shelves or UPS units.
- Phones and cameras brought into a hall that bans them.
- Reaching into a neighbouring cage, which can break another tenant's service.
- Drives left behind, with no plan for data media.
- Debris and packaging left in the hall after the job.
How do you build a removal pack before the visit?
Build the pack in this order: get the operator's contractor requirements, produce a hall-specific RAMS and method statement, request the permit and access, confirm insurance and crew names, book the dock and lift, and agree the isolation and handback steps. Submit early, because approvals take time and vary by operator.
- Request the operator's contractor pack and any forms.
- Walk the hall with the facility contact, and note routes, tile areas and isolation points.
- Write the RAMS and method statement for that hall and rack list.
- Agree isolation with the facility, in writing.
- Submit the crew list with IDs, exactly as they'll appear on the day.
- Attach insurance and competence evidence.
- Apply for the permit to work after RAMS approval, for the correct window.
- Book the loading bay, goods lift and gate passes.
- Agree escort, tool register and entry and exit checks.
- Hold a pre-start briefing, and close out the permit and the handback record afterwards.
Next step
If you're planning equipment removal from a UAE data hall, send us the operator's contractor pack, your rack list and your target dates. We'll align the RAMS and method statement with the operator's requirements and plan access, lifting, data media handling and records. MAH Recycling holds ISO 45001:2018 for occupational health and safety, but the facility's own rules always come first. WhatsApp +971 58 903 8823 or email info@mahrecycling.ae to arrange a site inspection. See our page on data centre decommissioning in the UAE.
About this guide
Written by: MAH Sustainability Team. Last reviewed: 26 November 2026.
Based on: Sharjah's OSHJ Code of Practice on permit to work, public descriptions of Abu Dhabi's OSHAD-SF, operator and university data centre access standards, and published UAE operator checklists.
Limits: I found no single UAE-wide rulebook for data hall contractors, and I didn't review any UAE colocation operator's private contractor pack. Requirements vary by operator and emirate. This isn't legal or safety advice.